Dec. 8th- Update on trail design – We are now at 90% design. Switch backs and grade modifications have been made. NPS and Boulder City to meet in field to work out final design spec’s at NPS Warehouse at completion point. We are looking for bid documents and bidding before end of January 2009. […]
RMLT construction status
I was looking at some old reports on our web site and I was quoted as saying we would be done hopefully in 2005, 2006, 2007, 2008, and now I’m saying spring 2009, let’s make that 2010. Things happen and when you are dealing with three Federal Land Management agencies, NDOT, private land owners, […]